Project Profile

Michuda Construction successfully completed the six-phase renovation of a 16-bed Pediatric Cardiac Intensive Care Unit (PCICU) within Advocate Christ Medical Center. The project balanced high-quality construction and a dynamic schedule while maintaining the hospital’s acute care operations, ultimately delivering a state-of-the-art facility for critical pediatric cardiac care.

PROJECT PROFILE

Advocate Christ Medical Center – Pediatric Cardiac Intensive Care Unit (PCICU) Renovation

Location: Oak Lawn, Illinois Client: Advocate Christ Medical Center Engineer: Grumman/Butkus Associates, Dickerson Engineering Architect: Matthei & Colin Associates Size: 8,100 SF Delivery Method: Construction Manager at Risk

PROJECT OUTCOME

Michuda Construction successfully completed the six-phase renovation of a 16-bed Pediatric Cardiac Intensive Care Unit (PCICU) within Advocate Christ Medical Center. The project balanced high-quality construction and a dynamic schedule while maintaining the hospital’s acute care operations, ultimately delivering a state-of-the-art facility for critical pediatric cardiac care.

PROJECT SCOPE

Michuda Construction oversaw the renovation of the PCICU, transforming the existing space into a cutting-edge unit designed to deliver superior care to young patients. The project scope included:

  • Complete Interior Renovation: Upgraded patient rooms, nurse stations, and family waiting areas with enhanced finishes and functional layouts.

  • MEP System Upgrades: Replacement and reconfiguration of mechanical, electrical, and plumbing systems to accommodate the latest medical technology and patient care requirements.

  • Mold Remediation and Exterior Wall Insulation Replacement: Addressed unforeseen issues with mold and failed insulation, ensuring a safe and compliant environment.

  • Enhanced Interior Finishes: Incorporated donor-requested upgrades during the final project phases, adding to the aesthetic appeal and functionality of the space.

CHALLENGES & SOLUTIONS

Occupied Facility Coordination:

  • Challenge: Construction within an active hospital environment while maintaining patient and staff safety.

  • Solution: Executed the project in six carefully planned phases, implementing rigorous infection control measures and coordinating with hospital staff to minimize disruption.

Unforeseen Conditions:

  • Challenge: Discovery of mold and insulation failure at exterior walls mid-project.

  • Solution: Adapted the schedule to include mold remediation and insulation replacement during each phase, maintaining progress without compromising quality.

Late-Stage Enhancements:

  • Challenge: Incorporating donor-requested enhanced interior finishes during the final phase.

  • Solution: Worked collaboratively with stakeholders to integrate the upgrades seamlessly, maintaining budgetary and schedule transparency.

VALUE TO THE CLIENT

Michuda Construction’s expertise in healthcare construction ensured the successful delivery of a state-of-the-art PCICU. Despite unexpected challenges, the project was completed with minimal impact on hospital operations and provided a safe, modern, and welcoming environment for pediatric cardiac care.