Nurse Call System Upgrades
Client
Advocate Aurora Health
Industry
Healthcare
Delivery Method
CM at Risk
Architect
Peak Electric
Project Profile
Michuda Construction is leading the system-wide nurse call upgrade for Advocate Aurora Health, enhancing patient care and communication capabilities across multiple sites. The upgrades, featuring the installation of the Rauland Responder 5 system, are being executed in multiple phases from 2022 through 2024, ensuring minimal disruption to hospital operations while providing state-of-the-art technology to patient care environments.
PROJECT PROFILE
Nurse Call System Upgrade
Client: Advocate Aurora Health
Location: Various Sites
Engineer & Architect: Peak Electric
Delivery Method: Construction Manager at Risk
PROJECT OUTCOME
Michuda Construction is leading the system-wide nurse call upgrade for Advocate Aurora Health, enhancing patient care and communication capabilities across multiple sites. The upgrades, featuring the installation of the Rauland Responder 5 system, are being executed in multiple phases from 2022 through 2024, ensuring minimal disruption to hospital operations while providing state-of-the-art technology to patient care environments.
PROJECT SCOPE
Michuda Construction is serving as the Construction Manager at Risk for the system-wide upgrade of the nurse call systems across Advocate Aurora Health facilities. The project focuses on improving patient communication and responsiveness by upgrading to the Rauland Responder 5 system, a state-of-the-art nurse call solution.
The scope of work includes:
Coordination with Low Voltage Vendors: Collaborating with specialized low voltage vendors to ensure proper integration and functionality of the new system.
ICRA Barriers: Installation and maintenance of Infection Control Risk Assessment (ICRA) barriers to protect patients and staff during construction activities, adhering to stringent infection control standards.
Device Removal and Replacement: Systematic removal and replacement of nurse call devices from patient headwalls, ensuring a seamless transition to the new technology.
Phased Implementation: Conducting the upgrades in multiple phases over a three-year period (2022-2024) to minimize disruption and maintain hospital operations.
CHALLENGES & SOLUTIONS
The project’s complexity required tailored strategies to address its challenges effectively:
Occupied Facility Coordination:Performing upgrades within active hospital environments demanded detailed planning and collaboration with hospital staff to minimize disruptions. Michuda scheduled activities during off-peak hours and implemented ICRA barriers to protect patient safety.
Phased Implementation:Upgrading multiple sites across the system required a phased approach. Michuda’s team developed and adhered to a strategic timeline to ensure each site’s needs were met without impacting overall hospital functions.
Vendor Coordination:Close coordination with low voltage vendors was critical for the successful integration of the Rauland Responder 5 system. Michuda worked collaboratively to ensure all installations were conducted seamlessly, meeting system specifications and operational requirements.
KEY PROJECT ELEMENTS
Enhanced Patient Care: Installation of the Rauland Responder 5 system to improve nurse-patient communication and responsiveness.
Infection Control: Implementation of ICRA barriers to ensure patient and staff safety during the upgrade process.
Phased Upgrades Across Multiple Sites: Strategic planning and coordination to minimize disruption while achieving system-wide improvements.