Hybrid OR & Clean Suite System

Client

Advocate Christ Medical Center

Industry

Healthcare

Delivery Method

CM at Risk

Architect

Matthei & Colin Associates

Project Profile

At Michuda Construction, our commitment to excellence and innovation in healthcare construction is unmatched. For the Hybrid OR project at Advocate Christ Medical Center, our project team demonstrated unwavering dedication to meeting the established timeline while prioritizing safety and minimizing disruptions to critical hospital services. Despite the challenges, Michuda’s team delivered a successful outcome, reflecting our dedication to advancing healthcare environments and supporting optimal patient care.

PROJECT SUMMARY

Hybrid OR & Clean Suite System Location: Advocate Christ Medical Center, Oak Lawn, IL Size: 2,600 sq.ft. Architect: Matthei & Colin Associates Delivery Method: Construction Manager at Risk / Design Assist Minority Participation: 31%

PROJECT SCOPE

Michuda Construction led the Construction Management at Risk services for the transformative expansion of Advocate Christ Medical Center’s Hybrid OR. The project involved:

  • 1,300 sq.ft. addition for the new Hybrid OR (Phase 1).

  • An additional 1,300 sq.ft. reserved for a future Hybrid OR (Phase 2).

  • Innovative design features, including a 45-degree angle placement of equipment for optimized space usage and a prefabricated Clean Suite ceiling system to streamline operations and enhance patient care.

CHALLENGES & SOLUTIONS

  1. Expansion of Hybrid OR Phase 1 and Phase 2

    • Challenge: Managing the phased expansion required precise coordination to ensure the new Hybrid OR suite integrated seamlessly with the hospital’s existing infrastructure. The project involved constructing a new 1,300 sq.ft. OR addition while preparing for a future OR expansion in the same footprint.

    • Solution: Michuda executed the project in four phases, focusing on the 2nd-floor mechanical room to support the 3rd-floor addition. This phased approach ensured each stage progressed without impacting hospital operations. We also utilized a designated pocket within the existing “circle drive” of the campus, ensuring construction activities remained organized and minimally disruptive.

  2. Building Exterior Aesthetics

    • Challenge: The building’s exterior needed to match the aesthetics of the existing outpatient pavilion, which featured precast concrete and a spandrel glass curtain wall.

    • Solution: Michuda meticulously aligned the new exterior with the existing structure, using precast concreteand spandrel glass to create a cohesive look. This attention to detail ensured that the expansion blended seamlessly with the surrounding campus.

  3. Maintaining Seamless Operations

    • Challenge: Ensuring uninterrupted operation of the existing OR during construction was critical, especially during multiple equipment shutdowns.

    • Solution: Michuda carefully coordinated multiple shutdowns, scheduling them to minimize disruption to hospital services. The strategic use of 45-degree angle equipment placement optimized the space within the Hybrid OR, while the integration of a prefabricated Clean Suite ceiling system facilitated a smooth installation, reducing time on site and enhancing the overall workflow.

OUTCOME

Michuda’s expertise in healthcare construction and close collaboration with Advocate Health allowed for a successful project delivery, on time and within the adjusted budget. The new Hybrid OR and future-ready space now enhance Advocate Christ Medical Center’s ability to deliver advanced surgical care to its patients. Our team’s innovative problem-solving and dedication to patient-centered design ensured that the hospital maintained seamless operations throughout the project, reflecting our commitment to excellence in every detail.

 